New Build Basement
This is part of a new build project with the basement forming part of the structural walls of the house.
A .250mm reinforced floor was constructed with a Sepoc single skin retaining wall filled with concrete.
The walls were then tanked with a cementitious flexible waterproof barrier containing cement binders and acrylic polymers.
An 8mm quad drain subsurface composite drainage system was then attached.
The excavation was then back filled and standard strip foundations formed and attached with dowel bars.
Block and beam floors where then installed.
Our client was very happy with a dry basement.
Building
Before & After
Take a look at the construction...
Customer Testimonial
I can fully recommend BK Elson Groundworks for small and medium sized civil engineering projects , based on the experience of a recently completed project for myself. This involved a significant basement excavation, support and reinforced concreting works , general excavation , drainage , foundation installation and hard and soft landscaping works.
All these works were completed to the highest standard of workmanship.
I have spent all my career employed in the construction industry , for the past 15 years as a Director of a medium sized PLC
Brian Alan Evans Bsc Building Science , MRCIOB .